Lead Time

Business📋 Agile DeliveryKanban

Also known as Customer Lead Time

The time from when work is asked for until it is delivered. It is the wait the customer feels.

Think of it like

It is like waiting for a pizza. The clock starts when you order, not when the cook starts.

Example

A customer asks for a new report on 1 March. Work starts on 10 March and ends on 14 March. The lead time is 13 days.

Why it matters

Customers do not care when work started. Lead time is the number that matches what they live through.

Formula

Lead time = date delivered - date requested

Definition

Lead time is how long a piece of work takes from the moment it is asked for until it is delivered. It counts the time the request sat waiting before anyone started. That wait is part of what the customer feels. So lead time is always as long as the cycle time, or longer. Teams track both the average and the spread.
Lead time is the long bar. It starts on the day of the request, so the 9 days of waiting count.

Common mistake

Starting the clock when work begins. That hides the days a request sat in a queue.

Key takeaways

  1. 1
    Starts at the ask. The clock runs from the request.
  2. 2
    Ends at delivery. It stops when the user has it.
  3. 3
    Waiting counts. Time in the queue is part of it.