Cost Performance Index (CPI)

Business📅 Scope, Schedule & CostProject Cost

Also known as CPI

Earned value divided by actual cost. Under 1 means the work costs too much.

Think of it like

It is like getting 80 cents of sweets for every dollar you spend. You get less than you paid for.

Example

Earned value is 30,000 and actual cost is 36,000. The index is about 0.83, so each dollar buys 83 cents of work.

Why it matters

It is the number most used to forecast what the whole project will cost.

Formula

CPI = EV / AC

Definition

The cost performance index shows how much value you get for each unit of money spent. You divide earned value by actual cost. A score of 1 means right on budget. Below 1 means over budget, and above 1 means under. It is often used to forecast the final cost of the project.
At 0.83, the cost index sits on the over budget side of 1. Each dollar buys 83 cents of work.

Common mistake

Hoping a low score will fix itself. Without a change in how the work is done, it rarely does.

Key takeaways

  1. 1
    EV over AC. Value done over money spent.
  2. 2
    1 is on budget. Below 1 is over budget.
  3. 3
    Forecasts. Used to predict the final cost.