Business📅 Scope, Schedule & CostProject Cost

Also known as SPI

Earned value divided by planned value. Under 1 means the work is behind.

Think of it like

It is like a speed check. You planned 10 pages a day but read 8, so you go at 0.8 of the plan.

Example

Earned value is 30,000 and planned value is 40,000. The index is 0.75, so the team is at three quarters of the planned pace.

Why it matters

As a ratio, it lets you compare small and large projects on one scale.

Formula

SPI = EV / PV

Definition

The schedule performance index shows how fast work is getting done against the plan. You divide earned value by planned value. A score of 1 means right on plan. Below 1 means behind, and above 1 means ahead. A score of 0.75 means only three quarters of the planned work is done.
At 0.75, the schedule index sits on the behind side of 1. Three quarters of the planned work is done.

Common mistake

Trusting it near the end. It always drifts back to 1 as the work finishes, even if the project is late.

Key takeaways

  1. 1
    EV over PV. Work done over work planned.
  2. 2
    1 is on plan. Below 1 is behind.
  3. 3
    Drifts to 1. It goes back to 1 at the end.