Cost Variance (CV)

Business📅 Scope, Schedule & CostProject Cost

Also known as CV

Earned value take away actual cost. Less than zero means you spent too much.

Think of it like

It is like buying 20 dollars of food and paying 25. You went 5 over.

Example

Earned value is 30,000 dollars and actual cost is 36,000. Cost variance is minus 6,000 dollars, so the work is over budget.

Why it matters

Overspend early in a project rarely fixes itself. This number spots it while there is time to act.

Formula

CV = EV - AC

Definition

Cost variance shows whether a project is under or over budget for the work done. You find it by taking actual cost away from earned value. A negative number means the work cost more than planned. A positive number means it cost less. It is one of the clearest early signs of money trouble.
Cost variance is the gap between earned value and actual cost on today's line.

Common mistake

Comparing spend with planned value instead of earned value. That mixes up being late with being over budget.

Key takeaways

  1. 1
    EV minus AC. Value done against money spent.
  2. 2
    The sign matters. Negative is over budget.
  3. 3
    Act early. Small gaps grow.