📅Cost Variance (CV)
Also known as CV
Earned value take away actual cost. Less than zero means you spent too much.
Think of it like
It is like buying 20 dollars of food and paying 25. You went 5 over.
Example
Earned value is 30,000 dollars and actual cost is 36,000. Cost variance is minus 6,000 dollars, so the work is over budget.
Why it matters
Overspend early in a project rarely fixes itself. This number spots it while there is time to act.
Formula
CV = EV - ACDefinition
Common mistake
Key takeaways
- 1EV minus AC. Value done against money spent.
- 2The sign matters. Negative is over budget.
- 3Act early. Small gaps grow.