Schedule Variance (SV)

Business📅 Scope, Schedule & CostProject Cost

Also known as SV

Earned value take away planned value. Less than zero means you are late.

Think of it like

It is like being on page 80 when your reading plan said page 100. You are 20 pages behind.

Example

Earned value is 30,000 dollars and planned value is 40,000. Schedule variance is minus 10,000 dollars, so the work is behind.

Why it matters

It puts a size on lateness, so you can tell a small slip from a big one.

Formula

SV = EV - PV

Definition

Schedule variance shows whether a project is ahead of or behind its plan. You find it by taking planned value away from earned value. A negative number means less work is done than planned. A positive number means the team is ahead. It is given in money, not days.
On the line for today, this is the gap between the work done and the work planned.

Common mistake

Reading it as days. It is a money's worth of work, so turn it into time with care.

Key takeaways

  1. 1
    EV minus PV. Work done against work planned.
  2. 2
    The sign matters. Negative is behind.
  3. 3
    In money. Not in days.